OVERHEAD CRANES

Overhead crane: the building is part of the crane project

An overhead crane travels on runway beams fixed to the building, so the building is not background — it is part of the machine. Span, rail height, headroom and the runway structure decide what can be installed before any crane is chosen, and they are the values most enquiries are missing.

IN THIS FAMILY

Members of this family

What the building has to provide, how to collect span and hook height, and when the arrangement has to change.

What has to exist before a crane can be quoted

Four things belong to the building, and each one can rule out an arrangement on its own. Check them before comparing cranes.

ItemWhat it decidesWhat to check
Runway beams and columnsWhether a crane can be carried at all, and what wheel loads the structure can takeThe runway drawing, the column spacing and the condition of the beams and their connections
Rail and its alignmentHow the crane travels, and how much of the wheel load is applied unevenlyRail type, fixings, joints and alignment along the run
HeadroomWhether the crane and the hoist body fit above the highest hook positionThe clear height at the highest point of travel, including trusses, ducts and lights
Power and controlWhere the supply comes from and how the crane is fed along its travelThe supply available at the building, and the route for the conductor or festoon run

A crane quotation that does not state what it assumes about the runway and the building has left the largest risk with the buyer.

Span, hook height and lift: measure, do not estimate

Span is the distance between the rail centrelines, not the distance between the walls and not the column spacing. The three values below are usually measured on site, and each one turns into a different part of the crane.

  • Span: tape between the rail centrelines at several stations along the run, and record the variation.
  • Rail top elevation: the datum for hook height and for the crane's overall height.
  • Hook height and lift: the highest and lowest working positions, plus the load, the sling and the hook block.
  • End approach: how close the hook has to come to each end wall or column.
  • Travel length: how far the crane has to run, and what stops it at each end.

Start with the single-girder arrangement

For a workshop bay at moderate span, a single-girder crane is the usual starting point: one main girder, a trolley below or beside it, and a lower overall height above the rail. It leaves less room for the hook to rise than a double-girder arrangement, which is why the headroom check comes first.

  • Single girder: lower above the rail, and the trolley takes height below the girder.
  • Double girder: two girders with the trolley on top, so the hook can rise between them — and the crane is taller.
  • The girder count does not set the duty class. That is calculated from the cycle.
  • The runway and columns have to be checked against the wheel loads of the crane actually proposed.

This page describes arrangements, not a supply commitment. The configuration for your bay is confirmed on the drawing and in the quotation.

What to send before a quotation

ValueWhy it changes the answer
Crane span (rail centres)The crane is built to this value; it is not the column spacing
Column spacingSets the runway span and the number of supports
Rail top elevationThe datum for hook height and overall crane height
Clear headroomDecides whether the arrangement fits at all
Hook height and liftTurns the building height into a working range
Load and attachmentSets the hoist, the trolley and the hook arrangement
Duty and cycleSets the class of each mechanism
Runway and column detailsSets the wheel loads that have to be carried, and who checks them
Power supply and control positionSets the feed, the control arrangement and the operator's position
Destination and documentsSets the documentation, the power arrangement and the packing

What the quotation should state

  • The arrangement, the span it is built to and the hook height it achieves
  • The wheel loads, and whether the runway, rail and end stops are in scope
  • The hoist, trolley and control package, and what is excluded
  • The duty class of each mechanism, with the cycle it was calculated from
  • The documents, the installation scope and who commissions the crane
  • The inspection requirements at the destination, and who arranges them

The eleven values to measure in the bay before a crane is quoted, and the eight items to compare between offers, are on the crane planning worksheet.

LET'S DISCUSS YOUR JOB

Planning a crane for a workshop bay?

Send the span, the bay layout, the headroom and who is supplying the runway. We can point out what has to be agreed before installation.

WhatsApp our team ↗

Or email our team directly. If the form does not load, use email or WhatsApp.

Send your enquiry directly to our team. Our form service processes your message and we use your details to respond to this enquiry. If the security check does not appear after a few seconds, use the email or WhatsApp links below — your answers are copied into the message. Privacy & enquiries.

Security check not loading, or prefer a direct message? Send the same details by email or WhatsApp — your answers are copied into the message.

These links open your email app or WhatsApp. Review the message and send it there.

COMMON QUESTIONS

Questions about overhead cranes

What is the difference between span and column spacing?

Span is the distance between the two rail centrelines, and it is the value the crane is built to. Column spacing is the distance between building columns, which sets the runway span and the number of supports. They are usually close and often different, and a crane ordered to the column spacing can arrive too long or too short.

Can an overhead crane be added to an existing building?

Often, but the runway and columns have to be checked against the wheel loads of the proposed crane, and the headroom has to be measured rather than read from a drawing. Where the building was never designed for a crane, the runway may become the larger part of the project.

Single girder or double girder?

Start with the headroom and the span. A single-girder crane is lower above the rail, which suits buildings with limited height; a double-girder crane lets the hook rise between the girders but needs more room above. The comparison page sets out the differences row by row, and the quotation confirms the configuration.

Who supplies the runway?

It varies by project. Some quotations include the runway beams and rails, others supply the crane and leave the runway to the building contractor. The scope has to be written into the quotation either way, together with who checks the column loads.