OVERHEAD CRANE COMPARISON
Single girder vs double girder crane
The girder count changes where the hoist sits, how much of the building height becomes hook height, and what the runway has to carry. It does not set the duty class by itself, and it does not settle the project cost on its own. Compare the two arrangements on the same lifting task and the same building section, then let the quotation confirm the configuration.
What the two arrangements actually change
A single-girder crane has one main bridge girder spanning the runway. Its hoist trolley runs under the bottom flange or is carried beside the girder, so the lifting unit hangs below or alongside the main member. A double-girder crane has two main girders braced together, with the trolley running on rails on top of them. Almost everything that differs follows from that one change.
- Single girder: one main member, a lighter bridge, and a trolley that sits under or beside it.
- Double girder: two main members braced together, a trolley that runs between them on top, and a heavier bridge.
- The hoist itself can be similar. The difference is the structure that carries it and the space that structure needs.
This page compares engineering arrangements. It is not a product listing and does not confirm that a particular arrangement is available. The configuration discussed for your project is confirmed in the enquiry and the quotation.
The comparison, row by row
Use the same span, the same load and the same building section on both sides. A comparison that changes two variables at once only shows which supplier wrote the shorter quotation.
| Question | Single girder | Double girder |
|---|---|---|
| Bridge structure | One main girder, with the trolley running below it or alongside it | Two main girders braced together, with rails on top for the trolley |
| Where the hook can go | The trolley hangs below the girder, so it uses part of the height between rail and roof | The hook can rise between the girders, so more of the building height can become hook height |
| Height above the rail | Lower overall, because there is no second girder and no trolley on top | Taller overall: two girders, trolley rails and, on larger units, a walkway or platform |
| Span | In practice, shorter and medium spans where the girder depth still fits the building | In practice, longer spans, where two girders give the stiffness and torsional resistance one member struggles to provide |
| Duty and fatigue | The class comes from the cycle and the load spectrum, not from the girder count | The same calculation applies; two main members and a top-running trolley add structural redundancy at high duty |
| Runway and columns | Usually a lighter crane dead weight, so lower wheel loads on the runway | Usually a heavier crane dead weight, so higher wheel loads for the runway, corbels and columns to carry |
| Quotation scope | One girder, end carriages, trolley and hoist package; runway works are usually separate | Two girders, trolley rails, end carriages, walkway or platform and a larger hoist package; runway works are still separate |
No figure is given for span, height or capacity. Those values come from your building survey and the proposed design.
Hook height and headroom are the first thing to compare
Two cranes can have the same span and the same rated load and still leave you with different hook height, because the lifting unit sits in a different place. On a single girder the trolley hangs under the bridge, so the distance from rail top to the highest hook position includes the trolley body. On a double girder the hook can be brought up between the girders, so the same building height can give a higher hook position, but the crane needs more room above the rail.
- Rail top to the highest hook position
- Crane top to the roof, truss or nearest service
- Horizontal clearance from the hook to the column at each end of travel
A higher hook position is not free. A double-girder crane is taller above the rail, so a low roof can rule it out even where the hook would go higher. Measure the building section, not only the span.
Span and duty: what the girder count does and does not decide
Longer spans and heavier duty favour two girders, because the bridge has to carry the trolley and load without excessive deflection, and because two braced members resist the torsional load a travelling trolley applies. That is a structural argument, not a rule with a fixed span limit. The practical limit is set by the girder depth the building can accept, the deflection limit the project agrees and the crane's own mass.
- Duty class is calculated from how often each mechanism runs and how heavily it is loaded.
- The same class can be quoted on either arrangement. A double-girder crane is not automatically a higher class.
- Ask for the class of each mechanism with its basis, and compare that with the cycle you actually run.
Two main members add structural redundancy at long span and high duty, but the class on the quotation still has to come from your own cycle profile.
What to measure before you compare
The comparison is only as good as the site data behind it. These are the values that decide which arrangement can fit, and most of them can be measured without a crane supplier on site.
| Value | Where it comes from | Why it changes the answer |
|---|---|---|
| Column spacing (bay spacing) | Building drawing, or tape between column centres along the runway | Sets the runway beam span and the number of supports; it is not the same as the crane span |
| Crane span (rail centre distance) | Tape between the two rail centrelines, at several stations | The crane is built to this value; a column spacing that looks right can still give a different rail distance |
| Rail top elevation | Survey instrument or level to the top of each rail | Fixes the datum for hook height and for the crane's overall height |
| Clear headroom | Measure at the highest point of crane travel, including roof trusses, services and lights | Decides whether a taller double-girder crane fits at all |
| Hook height required | The highest and lowest pick, plus the load and sling depth | Turns the building height into a usable lifting range |
| Lifting cycle profile | Lifts per hour in the busiest shift, operating hours per shift, working days per year, and the usual load as a share of capacity | Sets the duty class and the fatigue case for the bridge and mechanisms |
| Runway and column capacity | Structural drawings and the wheel loads from each crane supplier | A heavier crane changes the wheel loads the runway and columns must carry |
| End approach | Distance from the hook at end travel to the nearest column or wall | A longer end carriage or a different trolley can reduce the usable travel |
If a value is missing, say so. A comparison built on an assumed span or an assumed roof height is a guess with a table around it.
The same measurements, with a blank column to write your own values in, are on the crane planning worksheet.
How to compare the two quotations
Put both enquiries on the same brief: same load, same lifting positions, same span, same hook height, same duty profile and same destination. Then compare five things line by line.
- The bridge and trolley arrangement, including the hoist model and trolley travel
- The dimensions that set hook height: rail top to hook, crane top to roof, and end approach
- Wheel loads and the runway, rail and end-stop scope, stated as included or excluded
- The duty class of each mechanism, with the cycle it was calculated from
- Documents, packing, delivery terms and the works each party performs
A single-girder quotation is often lower on the equipment line because the bridge contains less steel. That does not settle the project cost: the double-girder option may remove a runway or building change, or the single-girder option may need a deeper runway beam. Compare the total scope, not the crane line alone.
If the comparison still leaves two arrangements open, send the span, the hook height and the duty you are designing to on the enquiry form; the answer for your building is more useful than a general preference.
LET'S DISCUSS YOUR JOB
Comparing a single-girder and a double-girder layout?
Send the span, the building section and the lifting cycle. We can point out which values the comparison depends on and which are still missing.
WhatsApp our team ↗Or email our team directly. If the form does not load, use email or WhatsApp.
COMMON QUESTIONS
Questions about single girder vs double girder crane
Is a double-girder crane stronger than a single-girder crane?
It has two main members instead of one and a trolley that runs on top, so it can be the better structural choice at long span and high duty. That is not the same as stronger for every job: rated load and duty class are separate values, and a single-girder crane built for the same load can be adequate at a shorter span. Compare the arrangement against the span, the hook height and the cycle.
Does a double-girder crane give more hook height?
Usually more of the building height can become hook height, because the hook rises between the girders. The crane is also taller above the rail, so it needs more room under the roof. Ask for rail-top-to-hook and crane-top-to-roof on the same drawing, and check both against the building section.
Can the same runway carry either arrangement?
Not automatically. The two cranes have different dead weight, wheel loads and end carriage dimensions. The runway, rails, end stops and columns have to be checked against the wheel loads and wheelbase of the crane actually proposed, even when the span is the same.
Which arrangement costs less?
The equipment line for a single-girder crane is usually lower because the bridge contains less steel. The project cost can move the other way if the single-girder option needs a deeper runway beam or more building work, or if the double-girder option is needed to reach the hook height. Compare quotations on the same brief and the same scope.
Do you supply both arrangements?
This page is an engineering comparison, not a product listing. Send the span, the building section and the cycle, and we will confirm which arrangement can be discussed for your project and what the quotation covers.
