WORKSHEET
Crane planning worksheet: 11 site measurements and 8 quotation differences
Two lists to take to the bay before you ask anyone for a price: what has to be measured, and what has to be compared once quotations arrive. The measurement list is also published as a CSV you can fill in and send with your enquiry.
11 values to measure before you ask for a price
Measure at the bay, not from a drawing alone, and write the value and the date next to each row. A missing value is a question to ask, not a number to estimate.
| No. | What to measure or record | How to measure it | What it decides | The mistake we see | Your value |
|---|---|---|---|---|---|
| 1 | Rail centre distance (span), or working radius for a jib | Steel tape or total station between rail centre lines, read at both ends and at mid-bay | Bridge and end-carriage width, runway beam size, and whether an existing crane can be reused | Measuring wall to wall, or using the building width instead of the rail centres | |
| 2 | Hook height and headroom | Floor to the hook saddle at the top of travel, plus floor to the lowest obstruction above the crane | Hoist lift, rope reeving, and whether a low-headroom hoist is needed | Quoting the roof height as the hook height, and forgetting the hook block itself | |
| 3 | Bay length and end-stop positions | Tape from end stop to end stop along the runway, and mark the pick and set-down points on the floor | Crane travel, power-feed length, and festoon or conductor-bar length | Planning travel from the building length instead of from where the crane can actually stop | |
| 4 | Clearance envelope | Measure to columns, roof trusses, services, lighting and any adjacent crane, at the tightest point | Overall crane height, end-carriage approach, and whether the crane fits at all | Checking the middle of the bay and not the ends, where clearances are usually tightest | |
| 5 | Floor, foundation or runway beam condition | Slab thickness and condition, or the beam section and its supports; note who owns each | Whether a free-standing frame, a foundation or a building-mounted runway is possible, and who has to prove it | Assuming a floor will take the load because a forklift already drives on it | |
| 6 | Rail type and joint condition, where a runway exists | Rail section, joint step and gap, clip or weld condition, and wear across the rail head | Whether the existing runway can carry a new crane, and what has to be corrected before it arrives | Ordering the crane before the runway is surveyed, then treating track problems as crane problems | |
| 7 | Power supply at the feed point | Voltage, phase and frequency measured at the available feed point, the distance to the crane, and the isolator position | Hoist motor, control voltage, cable or conductor bar, and whether a transformer is needed | Quoting from the plant nominal voltage without checking the point the crane will actually connect to | |
| 8 | Delivery and erection access | Door widths and heights, turning space, floor capacity along the route, and the lifting equipment available on site | Whether the crane arrives assembled, in sections, or in pieces joined on site | Discovering at delivery that the end carriage does not pass the door | |
| 9 | Environment | Temperature range, dust, humidity, washdown, salt or outdoor wind, and any hazardous-area classification | Enclosure rating, finish, lubricant, and whether a standard hoist suits the location | Recording the site as indoor when the bay stands open to the yard | |
| 10 | Load geometry and handling points | Weight, shape, centre of gravity, lifting points, and the rigging that will be used | Hook approach, spreader or below-the-hook device, and the headroom the rigging consumes | Sizing on the load weight alone and forgetting rigging height and spread | |
| 11 | Working cycle | Count lifts during a busy shift, record hours per shift and shifts per day, and note the longest and the average lift | Duty class, motor rating, brake and hoist selection | Guessing a few lifts a day for a production bay, or sizing for the peak and never for the average |
The same eleven rows are in the CSV, with an empty Your value column: fill it in and send it with your enquiry.
Two quotations, same tonnage: the eight items that explain the difference
When two offers for the same rated load differ, the reason is almost never the rating. Compare these eight items line by line, and ask each supplier the question in the last column.
| Item | What to compare | Where the difference comes from | Ask each supplier |
|---|---|---|---|
| Duty class and motor rating | The classification printed on the datasheet and the motor rating behind it | A higher duty class needs a larger motor, brake and gearbox for the same tonnage | Which duty class is this quoted at, and what cycle did you assume? |
| Span and hook height | Rail centres, hook height, and the crane height at the tightest point | Steel weight and hoist lift both grow with span and height, so equal tonnage is not equal crane | Is the span in your quotation the rail centre distance I measured? |
| Hoist arrangement and rope reeving | Hoist model, reeving, and the hook approach that results | Reeving changes headroom, speed and the number of rope parts | How many rope falls are quoted, and what hook approach does that give me? |
| Controls and power feed | Pendant, radio or cabin, and festoon, conductor bar or cable reel | Controls and power feed are frequently quoted as options, and they change the electrical scope | Which control arrangement and power feed are included, and who installs them? |
| Runway and rails in scope | Whether rails, runway beams, brackets and foundations are supply, supply-and-install, or excluded | The runway is often the largest single difference between two quotations for the same crane | Is the runway in your scope, and if not, who signs off its survey? |
| Installation, commissioning and load test | Who erects, who commissions, who performs the load test, and who signs the handover | Site labour, crane hire and supervision sit in this line and vary by project | Who does the erection and the load test, and what document do I get at handover? |
| Documents and acceptance | Drawing set, test records, manual language, spare-parts list, and the stated acceptance criteria | Document packages differ between markets and suppliers, and rework after arrival is expensive | Send the document list you issue with this model, including the manual language. |
| Delivery terms and packing | Incoterm and delivery point, packing type, and who arranges insurance and unloading | The same equipment can be quoted at different delivery points and packing standards | Which delivery term is this price based on, and what packing does it assume? |
Copy this block once per quotation. Two offers are comparable when every line has an answer, not when the totals look similar.
What this worksheet does not do
Nothing on this worksheet is a specification. Capacity, span and lifting height are confirmed for the quoted configuration; prices, delivery dates, payment and warranty terms are agreed in the quotation for your project. Where a value depends on your building, your standard or your supplier document, the worksheet leaves it to that document rather than filling it in.
How to cite this worksheet
Krandura, Crane planning worksheet, https://krandura.com/engineering/crane-planning-worksheet/, generated 2026-11-26
If you quote a row from this page, cite it with that line so the reader can check the version and the date.