WORKSHEET

Crane planning worksheet: 11 site measurements and 8 quotation differences

Two lists to take to the bay before you ask anyone for a price: what has to be measured, and what has to be compared once quotations arrive. The measurement list is also published as a CSV you can fill in and send with your enquiry.

11 values to measure before you ask for a price

Measure at the bay, not from a drawing alone, and write the value and the date next to each row. A missing value is a question to ask, not a number to estimate.

No.What to measure or recordHow to measure itWhat it decidesThe mistake we seeYour value
1Rail centre distance (span), or working radius for a jibSteel tape or total station between rail centre lines, read at both ends and at mid-bayBridge and end-carriage width, runway beam size, and whether an existing crane can be reusedMeasuring wall to wall, or using the building width instead of the rail centres
2Hook height and headroomFloor to the hook saddle at the top of travel, plus floor to the lowest obstruction above the craneHoist lift, rope reeving, and whether a low-headroom hoist is neededQuoting the roof height as the hook height, and forgetting the hook block itself
3Bay length and end-stop positionsTape from end stop to end stop along the runway, and mark the pick and set-down points on the floorCrane travel, power-feed length, and festoon or conductor-bar lengthPlanning travel from the building length instead of from where the crane can actually stop
4Clearance envelopeMeasure to columns, roof trusses, services, lighting and any adjacent crane, at the tightest pointOverall crane height, end-carriage approach, and whether the crane fits at allChecking the middle of the bay and not the ends, where clearances are usually tightest
5Floor, foundation or runway beam conditionSlab thickness and condition, or the beam section and its supports; note who owns eachWhether a free-standing frame, a foundation or a building-mounted runway is possible, and who has to prove itAssuming a floor will take the load because a forklift already drives on it
6Rail type and joint condition, where a runway existsRail section, joint step and gap, clip or weld condition, and wear across the rail headWhether the existing runway can carry a new crane, and what has to be corrected before it arrivesOrdering the crane before the runway is surveyed, then treating track problems as crane problems
7Power supply at the feed pointVoltage, phase and frequency measured at the available feed point, the distance to the crane, and the isolator positionHoist motor, control voltage, cable or conductor bar, and whether a transformer is neededQuoting from the plant nominal voltage without checking the point the crane will actually connect to
8Delivery and erection accessDoor widths and heights, turning space, floor capacity along the route, and the lifting equipment available on siteWhether the crane arrives assembled, in sections, or in pieces joined on siteDiscovering at delivery that the end carriage does not pass the door
9EnvironmentTemperature range, dust, humidity, washdown, salt or outdoor wind, and any hazardous-area classificationEnclosure rating, finish, lubricant, and whether a standard hoist suits the locationRecording the site as indoor when the bay stands open to the yard
10Load geometry and handling pointsWeight, shape, centre of gravity, lifting points, and the rigging that will be usedHook approach, spreader or below-the-hook device, and the headroom the rigging consumesSizing on the load weight alone and forgetting rigging height and spread
11Working cycleCount lifts during a busy shift, record hours per shift and shifts per day, and note the longest and the average liftDuty class, motor rating, brake and hoist selectionGuessing a few lifts a day for a production bay, or sizing for the peak and never for the average

The same eleven rows are in the CSV, with an empty Your value column: fill it in and send it with your enquiry.

Two quotations, same tonnage: the eight items that explain the difference

When two offers for the same rated load differ, the reason is almost never the rating. Compare these eight items line by line, and ask each supplier the question in the last column.

ItemWhat to compareWhere the difference comes fromAsk each supplier
Duty class and motor ratingThe classification printed on the datasheet and the motor rating behind itA higher duty class needs a larger motor, brake and gearbox for the same tonnageWhich duty class is this quoted at, and what cycle did you assume?
Span and hook heightRail centres, hook height, and the crane height at the tightest pointSteel weight and hoist lift both grow with span and height, so equal tonnage is not equal craneIs the span in your quotation the rail centre distance I measured?
Hoist arrangement and rope reevingHoist model, reeving, and the hook approach that resultsReeving changes headroom, speed and the number of rope partsHow many rope falls are quoted, and what hook approach does that give me?
Controls and power feedPendant, radio or cabin, and festoon, conductor bar or cable reelControls and power feed are frequently quoted as options, and they change the electrical scopeWhich control arrangement and power feed are included, and who installs them?
Runway and rails in scopeWhether rails, runway beams, brackets and foundations are supply, supply-and-install, or excludedThe runway is often the largest single difference between two quotations for the same craneIs the runway in your scope, and if not, who signs off its survey?
Installation, commissioning and load testWho erects, who commissions, who performs the load test, and who signs the handoverSite labour, crane hire and supervision sit in this line and vary by projectWho does the erection and the load test, and what document do I get at handover?
Documents and acceptanceDrawing set, test records, manual language, spare-parts list, and the stated acceptance criteriaDocument packages differ between markets and suppliers, and rework after arrival is expensiveSend the document list you issue with this model, including the manual language.
Delivery terms and packingIncoterm and delivery point, packing type, and who arranges insurance and unloadingThe same equipment can be quoted at different delivery points and packing standardsWhich delivery term is this price based on, and what packing does it assume?

Copy this block once per quotation. Two offers are comparable when every line has an answer, not when the totals look similar.

What this worksheet does not do

Nothing on this worksheet is a specification. Capacity, span and lifting height are confirmed for the quoted configuration; prices, delivery dates, payment and warranty terms are agreed in the quotation for your project. Where a value depends on your building, your standard or your supplier document, the worksheet leaves it to that document rather than filling it in.

How to cite this worksheet

Krandura, Crane planning worksheet, https://krandura.com/engineering/crane-planning-worksheet/, generated 2026-11-26

If you quote a row from this page, cite it with that line so the reader can check the version and the date.