SPAN, HEIGHT & HEADROOM

Crane span and hook height: what the bay allows

A crane can be correct on paper and still miss the load, because four different numbers decide whether it fits the bay: span, hook approach, hook height and lift height. They are often quoted with the same words and from different datums. This page is a measuring guide, not a product listing: it sets out what each figure means, the six measurements to take at the building, and the figures to compare in two quotations.

Four numbers decide whether the crane fits

Span, hook approach, hook height and lift height are separate figures. Two of them are horizontal, two are vertical, and each one is measured from a datum that has to be named. When a supplier quotes a span but not an approach, or a hook height without saying whether it is measured from the floor or from rail top, the quotation cannot be checked against the bay. Fix the four figures first and the equipment discussion has something to stand on.

FigureWhat it describesWhere the number comes from
SpanHorizontal distance between the two runway rail centrelinesThe rails in your building, measured or taken from the bay drawing. The building width is not the span
Hook approachHorizontal distance from a runway rail centreline to the hook centre at its nearest working positionThe crane arrangement and hoist envelope, confirmed for each end in the quotation
Hook heightVertical position of the hook at its highest working point, from a stated datumRail level, crane depth, trolley or hoist envelope, hook block and reeving
Lift heightVertical travel between the highest and the lowest hook positionThe duty cycle: where the load is picked up, where it is set down, and how much clear height the lift needs

Ask for every vertical figure with its datum: floor level, rail top or the hook saddle. A height without a datum is a number that cannot be checked.

Span: rail centre to rail centre, not wall to wall

An overhead crane runs on two rails carried by the runway beams, and the span is the distance between the centreline of those rails. The bay width on a building drawing includes the columns, the runway brackets and the clearance between them, so it is always larger than the crane span. Ordering from the building width produces a crane that does not fit between the rails; ordering from one tape reading at one end produces a crane that may not fit the other end.

  • Measure between rail centrelines at both ends of the runway and at the middle, and record all three readings.
  • Record the rail top level on each side: two rails at different levels change the effective hook height and the wheel contact.
  • Note how the rail is fixed, because a pad, a clip or a welded base changes the effective centreline and the height.
  • Check that both rails are the same section and that neither has been replaced or built up.
  • Compare the readings with the bay drawing; where they disagree, the site measurement is what the crane has to suit.

Rail alignment and level tolerances belong to the runway, not to the crane. The runway page sets out what the installation has to achieve before a crane is set on it.

Hook approach: why the hook stops short of the wall

The hook cannot travel to the end of the rail. The end carriage, the hoist body and the trolley all take up horizontal space, so the hook centre stops at some distance from the rail centreline. That distance is the hook approach, and it is not the same for every arrangement: a hoist carried under a single girder and a trolley running on top of two girders use the space differently, so the same bay can give a different usable width for the same span.

  • Mark every lifting point on the bay plan, including the ones close to a wall, a column or a door.
  • Measure from each lifting point to the nearest runway rail centreline, and do it at both ends of the bay.
  • State the approach you need at each end, not an average, because the two ends can differ.
  • Treat a load that has to be set down against a wall as an approach question before it becomes a span question.

No hook approach figure is published here. It is confirmed against the proposed hoist and end carriage, because it changes with the arrangement.

Hook height and lift height: two vertical numbers

Hook height is a position; lift height is a distance travelled. Hook height is measured from a named datum to the hook saddle at its highest working point. Lift height is the vertical travel between the highest and the lowest hook position. A quotation that gives only one of them leaves the other to be discovered on site, usually when the load will not clear a machine or a stack.

  • The building sets a maximum hook height: from rail top down to the floor, minus the crane girder, the trolley or hoist body, the hook block and the clearance the load needs.
  • The load sets the minimum: the hook has to reach high enough to lift the load clear of the floor, the machine or the stack it comes off.
  • The attachment consumes height as well: slings, spreader beams, magnets and grabs all sit between the hook and the load.
  • Where the required hook height does not fit, the arrangement changes before the rope length does: a lower-profile hoist, a different girder arrangement or a revised runway level.

A long lift in a low building usually changes the arrangement, not only the rope length.

Headroom above the crane and below the girder

There are two clearances, and both are measured to the lowest obstruction rather than to the roof deck. Above the crane, the structure has to clear the crane depth, and on a double-girder arrangement the trolley travelling on top of the girders. Below the girder, the hook block has to clear the load and the floor at its highest position.

  • Purlins, roof bracing, lights, cable trays, compressed-air lines and doors are obstructions even when the roof itself is high enough.
  • An adjacent crane on the same runway reduces the clear space, and so does a crane on a higher level crossing the same bay.
  • Side clearance to columns and walls matters for the end carriage and for access to the crane.
  • Measure the clear height at the lifting points, not only in the middle of the bay: roofs sag, services run at different heights and the lowest point is what counts.

The six measurements to take

Take these at the building, with the tape or level you actually used, and photograph each rail end with a scale in the frame. A sketch with six measured values is more useful than a catalogue page or a building drawing.

MeasurementHow to take itWhat it settles
Runway spanTape between rail centrelines at both ends and mid-bayThe span the crane has to suit, and whether the rails are parallel
Rail top level, each sideLevel or survey at several points along each railThe datum for hook height, and whether one rail sits higher
Clear height to the lowest obstructionFloor to purlin, service, light, door head or roof structureThe crane depth and hook block that can fit above the load
Distance from each rail to the end wall or columnTape along the runway at both endsThe hook approach available at each end
Hook height needed at each lifting pointFloor to the hook saddle with the attachment fittedThe vertical figure the crane has to reach
Load, attachment and lift pathWeigh or estimate the load; sketch the attachment and the pathCapacity, hook block size and the travel that has to stay clear

Leave a value blank when it has not been measured. A guessed span or hook height is worse than a blank one, because it is checked against the wrong bay.

How to compare two quotations on the same numbers

Two quotations can look similar and describe different working envelopes. Ask every supplier for the same figures, with the same datums, in writing, then compare them line by line. The most expensive question left open is not the price: it is whether the crane serves the lifting points you already have.

  • Span and rail centres the offer assumes.
  • Hook approach at each end, stated separately.
  • Hook height with its datum, and the lift height.
  • Headroom required above rail top, including the trolley on a double-girder arrangement.
  • End carriage length and wheelbase, which decide how much of the runway the crane occupies.
  • The load case the figures apply to: load, attachment, duty and the lifting points.

A quotation that repeats the span but omits the approach has not answered the fit question.

The six measurements above, plus the values the rest of the enquiry depends on, are on the crane planning worksheet, with a blank column to record each one.

What this page does not decide

This page does not decide capacity, duty class, the structural adequacy of the runway or the building, or the tolerances the installation has to meet. Those are separate questions with their own inputs. What it does is fix the four figures that decide whether a crane can serve the lifting points, and the six measurements that make those figures checkable before an order is placed.

No span, height, capacity or tolerance figure is published here. Every value is confirmed for the bay and the configuration quoted.

Once the six measurements are in hand, send them with the load and the destination on the enquiry form; the arrangement follows from those values, not from this page.

LET'S DISCUSS YOUR JOB

Checking whether a crane fits your bay?

Send the rail-to-rail span, the clear height and the hook height you need. We can point out which figures are still missing before a proposal is prepared.

WhatsApp our team ↗

Or email our team directly. If the form does not load, use email or WhatsApp.

Send your enquiry directly to our team. Our form service processes your message and we use your details to respond to this enquiry. If the security check does not appear after a few seconds, use the email or WhatsApp links below — your answers are copied into the message. Privacy & enquiries.

Security check not loading, or prefer a direct message? Send the same details by email or WhatsApp — your answers are copied into the message.

These links open your email app or WhatsApp. Review the message and send it there.

COMMON QUESTIONS

Questions about crane span and hook height

Is crane span the same as building width?

No. The span is the distance between the runway rail centrelines, inside the columns. The building width includes the columns, the runway brackets and the clearance between them, so it is always larger. Measure the rails, not the walls, and measure at both ends and the middle.

What is hook approach?

The horizontal distance from a runway rail centreline to the hook centre at its nearest working position. It is set by the end carriage and the hoist or trolley envelope, so it differs between arrangements. State the approach you need at each end and it is confirmed against the proposed hoist.

Is lift height the same as hook height?

No. Hook height is a position measured from a stated datum, usually the floor or rail top. Lift height is the travel between the highest and lowest hook positions. A quotation should give both, and say which datum the height is measured from.

Can the hook reach the end wall?

Only to its hook approach limit. Mark the lifting points on the bay plan first: if a point sits inside the approach, the arrangement, the span or the position of the runway has to change. The approach is confirmed per end, because the two ends can differ.

What should I send to confirm a crane fits my bay?

The six measurements on this page, the load and attachment, and photos of both rail ends with a scale. Unknown values can be left blank. A guessed span or hook height is checked against the wrong bay and produces a proposal that cannot be built.

Related reading