BUYING ECONOMICS
What drives the price of an overhead crane
The capacity on the nameplate tells you what the crane lifts. It does not tell you what the crane costs, because the same lifting task can be built around a short or a long span, a low or a high hook height, a light or a heavy duty cycle, and a supply scope that stops at the factory gate or ends with a commissioned crane. Price follows those decisions, not the tonnage alone. This page sets out which decisions move the number and how to compare offers built on the same brief. It publishes no prices, and any figure we give is tied to a defined scope.
The capacity is one input, not the answer
Two cranes rated for the same load can differ in girder depth, hoist frame, wheel loads and control equipment, because rated capacity only fixes the load chain: hook, block, rope or chain, drum, brake and the structure that carries them at the required factor. Everything that turns that load into a machine — span, hook height, duty cycle, travel speeds, environment, control method — is decided separately, and each of those decisions has a cost consequence.
That is why a per-tonne figure taken from another project is not a budget. It describes a different building, a different cycle and a different supply scope.
The blocks that make up the price
An overhead crane quotation is a set of blocks, not one number. Seeing the blocks separately is what lets you compare two offers and decide where to spend.
| Block | What sets its size | What the buyer decides |
|---|---|---|
| Bridge and end carriages | The span it has to cross, the hook height it has to reach and the duty it has to survive | Span from the building, hook height from the task, duty from the cycle |
| Hoist and trolley | Rated load, lift height, reeving, lifting speed and how often the brake works | Speed against control, single or twin hook, hoist frame that fits the girder |
| Electrics and controls | Number of motions, starting and stopping behaviour, where the operator stands | Pendant, radio or cabin; soft starting; positioning aids; interface to your own system |
| Runway and building works | The crane's wheel loads and the structure that has to carry them | Whether rails, corbels, columns and foundations are in your scope or the supplier's |
| Installation and commissioning | Site access, lift height, available power, whether production can stop | Supply only, supervised erection, or full installation and handover |
| Documentation and acceptance | What your site, insurer or authority will ask to see | Drawings, test records, language, third-party attendance, acceptance criteria |
| Packing, freight and terms | Volume, weight, destination, mode and who carries risk at each point | Delivery term, consolidation, unloading at site, insurance |
| Spares, training and support | Which parts stop the crane when they fail | Recommended spares, operator training, maintenance scope, response arrangement |
Order and grouping vary by supplier. What matters is that each block is either priced, included, or written down as an exclusion.
The decisions that move the number most
Some choices change a component. A few change the whole machine, and those are worth settling before you ask anyone for a price.
| Decision | Why it moves the cost | When to settle it |
|---|---|---|
| Span | Sets girder depth and steel weight, and through wheel loads it reaches into the runway and the building | Before the first budget enquiry: it comes from the building, not from the crane |
| Hook height and lift | Changes the hoist frame, the rope or chain length, the drum and often the girder height | Before the layout is fixed, because it competes with roof and services |
| Duty cycle | Fatigue life and component sizing follow the cycle and the load spectrum, not the peak load | Before comparing offers: a light and a heavy class are different machines |
| Control method | Pendant, radio and cabin change the operator's position, the wiring and the safety envelope | When the process is known: frequent accurate positioning usually pays for a better control |
| Environment | Heat, dust, moisture, corrosive atmosphere and outdoor duty change enclosure, finish, rope and brake specification | At enquiry: retrofitting protection costs more than specifying it |
| Speeds | Travel and lifting speed change motor, drive and brake size, and the structural loads that come with them | When the cycle time is known, not by default |
| Scope boundaries | Installation, runway, documentation and freight are often the largest difference between two quotes for the same crane | Before you compare totals, or the comparison is meaningless |
The cheapest way to move the number is not to shrink the crane. It is to remove scope you do not need: a shorter hook height, a lighter duty class that genuinely fits, a control method matched to how often the operator positions a load.
Why two quotes for the same capacity differ
Most of the gap between two offers is scope, not margin. These are the items that disappear quietly from the lower quote.
| Item | What the lower quote often leaves out | What to check in writing |
|---|---|---|
| Runway | Quoted as "by others" without saying who checks the rails, alignment or anchors | A named party for the runway, its survey and its acceptance |
| Installation | Equipment delivered, erection excluded, or erection included without supervision | Who erects, who supervises, who connects power, who signs handover |
| Hook height | A hook height assumed rather than measured from your drawing | The hook height and the datum it is measured from, on the drawing |
| Duty | Class stated without the cycle it was calculated for | The duty basis and the cycle profile it assumes |
| Controls | Basic pendant where the brief implied positioning control | The control method, the number of motions and the interface |
| Documents | Operating instructions only, no test records or drawings | The document list, the language and who issues each item |
| Freight and terms | Ex-works price compared against a delivered price | The delivery term and the point where risk and cost transfer |
| Spares | No recommended spares list, so the first failure stops the crane | The parts list and which items you should hold |
How to normalise two offers before you negotiate
Negotiation on a number that describes two different scopes only moves the scope, not the cost. Do this first.
- Write one brief: span, hook height and the datum, rated load, duty cycle with the load spectrum, control method, environment and destination
- Ask both suppliers to answer the same brief line by line, and to mark each item included, excluded or priced separately
- Put installation, runway, documentation, freight and spares on the same side of the comparison before you look at totals
- Ask what each supplier assumed where your brief was silent, and write those assumptions down
- Compare the operating limits each offer states, not only the headline capacity
- Only then compare totals, and negotiate on the items that differ in scope rather than on the headline number
If a supplier will not state an assumption in writing, treat it as excluded. That is the item that appears as a change order later.
Why this page carries no price
A published price for a crane of a given capacity is either a stripped configuration that nobody buys, or a number that is out of date before the enquiry arrives. Steel, freight, duty class, span and scope move it, and the same capacity in two buildings is two different machines. A "from" figure also sets an expectation that every later conversation has to argue with.
- We quote against a defined scope, so the number can be compared with another supplier's number
- We state what is excluded, because that is where project cost actually appears
- We do not publish prices, discounts or delivery promises on a web page
What to send to get a comparable number
- Span: rail centre to rail centre, and whether the runway already exists
- Hook height: from floor to hook, and the datum you measured from
- Rated load and the heaviest single lift, including any spreader or magnet
- Duty: lifts per hour, hours per day, and how often the crane runs at full load
- Control: pendant, radio or cabin, and how precisely the load has to be positioned
- Environment: indoor, outdoor, heat, dust, moisture, corrosive atmosphere, hazardous area
- Scope: who supplies the runway, who installs, who commissions, which documents your site requires
- Destination and delivery term, plus any site access limit on transport or lifting
Send these and the answer is a scope with a price attached to it. Send only a capacity and "how much" and the honest answer is a range of machines, not a number.
Send that brief on the enquiry form and ask each supplier the same questions; a quotation that answers the same list is the only one worth comparing.
LET'S DISCUSS YOUR JOB
Comparing crane prices or quotes?
Send the span, the hook height, the duty cycle and what the crane has to reach. We can tell you which of those still change the cost before you ask anyone for a number.
WhatsApp our team ↗Or email our team directly. If the form does not load, use email or WhatsApp.
COMMON QUESTIONS
Questions about what drives overhead crane price
Does the price depend only on the capacity?
No. Capacity fixes the load chain, but span, hook height, duty cycle, control method, environment and the supply scope decide how much structure and equipment that load needs. Two cranes with the same rated load in two different buildings are two different machines.
Why can't you publish a crane price on the page?
Because the number would describe a configuration, not your project. A published figure would have to assume a span, a hook height, a duty class and a scope, and every one of those changes the cost. We quote against a written scope instead, so the number can be compared.
Does span change the price more than capacity?
Often, yes. Span drives girder depth and steel weight, and through wheel loads it reaches into the runway and the building. Increasing capacity on a short span can cost less than keeping the capacity and stretching the span.
Is the runway included in a crane price?
Usually not, and it is the item most often left ambiguous. The runway, its rails, corbels, columns and foundations are a separate structural scope. Ask for a named party responsible for the runway survey and acceptance before you compare totals.
Can you price a crane from a photo or a capacity alone?
No. A photo does not give span, hook height, duty or the building's constraints, and those decide the structure. A capacity alone describes a family of machines. Send the measurements and the cycle and the answer becomes a scope you can compare.
What is the cheapest way to reduce the cost?
Remove scope you do not need rather than shrinking the crane below the duty. A hook height measured rather than assumed, a duty class that genuinely fits the cycle, and a control method matched to how often the operator positions a load usually move the number more than a smaller nominal capacity.
